Factors Hindering Quality Performance in Construction Projects: An Empirical Study
Abstract
Construction industry is crucial for the economy of any country. Learning from failure is important to reach effective quality performance in construction projects. This will, in turn, contribute to the development of the construction industry and the country as a whole. Although quality is an important criterion in the project management success, but it receives less attention than cost and time in project management literature. Moreover, critical success factors (CSFs) are identified more often than critical failure factors (CFFs) in construction literature. Hence, there is still a lack of attention on critical failure factors affecting quality performance in construction projects. Construction industry is full of uncertainties, especially in the current era of COVID-19 Pandemic. This adds to the necessity of studying critical failure factors in construction industry. This study aims to identify the critical factors that have adverse effect on quality performance in construction projects, address their relative importance, and suggest ways to attain good quality performance in construction projects. Based on literature review, an initial list of failure attributes of quality performance in construction projects was prepared. Then it was refined based on suggestions from experienced professionals in the construction industry in the Jordanian context. A questionnaire was distributed to experts in the construction industry. The responses were analyzed using Statistical Package for the Social Sciences (SPSS). The analyses used here are factor analysis and tests of its appropriateness. Using these analyses, the most critical factors that impede quality performance in construction were identified and ranked. The study revealed that the most influencing failure factors are the managerial factor, the culture and environment factor, and the contractor factor.
References
[2] Abiodun, O. E. , Segbenu, N. S. , & Oluseye, O. (2017). Factors affecting contractors’ performance in construction project delivery in Akure, Ondo State, Nigeria. Journal of Knowledge Management, Economics and Information Technology, 7 (4), 1- 23.
[3] Anoop, T., Asadi, S. S., Prasad, AVS., (2016). The Critical Success Factors affecting the performance of construction industry. International Journal of Civil Engineering and Technology (IJCIET) ,7(6), 669-675.
[4] Atkinson A.R. (1999). The role of human error in construction defects. Structural Survey. 17(4), 231-236.
[5] Babalola, H. I. , & Ojo, O. J. (2016). An Investigation into factors affecting the performance of public construction projects in Ondo State, Southwestern, Nigeria. Civil and Environmental Research, 8(1), 72-79.
[6] Babu, N. J. (2015). Factors affecting success of construction project. IOSR Journal of Mechanical and Civil Engineering, Ver. V, 12(2), 2320-2334.
[7] Bitamba, B.F.& An, S.H. (2020). Study on factors affecting the performance of construction projects in the Democratic Republic of the Congo. South African Journal of Industrial Engineering, 31(1), 12-25.
[8] Chan A. P. C., Scott D., Chan A. P. L. (2004). Factors affecting the success of a construction project. Journal of Construction Engineering and Management, ASCE, 130(1),153–155.
[9] Davidkumar, C. & Kathirvel, P. (2015). A study on factors influencing quality of construction Projects. International Journal for Research in Applied Science & Engineering Technology, 3 (5), 200-207.
[10] Delatte, N. (2010). Failure literacy in structural engineering. Engineering structures Journal, 32 (7), 1952-1954. https://doi.org/10.1016/j.engstruct.2009.12.015
[11] Dorcas, O. A. B., Elkanah, A. O., and John, O. O. (2019). Most critical factors responsible for poor project quality performance in building construction industry (A case study of three major cities in Nigeria). European International Journal of Science and Technology, 8(2), 1-14.
[12] El-sokhn, N. H. & Othman, A. A. E. (2014, May 27-29). Project failure factors and their impacts on the construction industry: a literature review [Paper presentation]. ICCAE-10 2014: 10th International Conference on Civil and Architecture Engineering. Military Technical College Kobry El-Kobbah, Cairo, Egypt.
[13] Ganesh S. M., (2016). Poor quality in Building projects. International Journal of Engineering Science & Research Technology, 5 (7), 1147-1153.
[14] Hair, J. F., Black, W. C., Babin, B. J., & Anderson R. E. (2010). Multivariate data analysis (7th ed.). Pearson Prentice Hall.
[15] Irfan, M., Thaheem, M.J., Gabriel, H.F., Malik, M.S.A. & Nasir, A.R. (2019). Effect of stakeholder’s conflicts on project constraints: a tale of the construction industry. International Journal of Conflict Management, 30 (4), 538-565. https://doi.org/10.1108/IJCMA-04-2019-0074
[16] Iyer, K. C., & Jha, K. N. (2006). Critical factors affecting schedule performance: Evidence from Indian construction projects. Journal of Construction Engineering and Management, 132(8), 871-881.
[17] Jha K. N. & Iyer K. C. (2006) Critical Factors Affecting Quality Performance in Construction Projects. Total Quality Management, 17 (9), 1155-1170.
[18] Jugdev, K. & Müller, R. (2005). A retrospective look at our evolving understanding of project success. Project Management Journal, 36(4), 19–31.
[19] KISAVI, J. M. & NGUGI, L. (2019). Critical factors and their influence on performance of road construction projects in Kiambu County, Kenya. International Journal of Scientific and Education Research, 3(3), 44-66.
[20] Kusi, M., Zhao, F. A, & Sukamani, D. (2018). Study of performance level of Nepalese construction firms in construction quality. North American Academic Research,1(5) ,137-153.
[21] Larsen, J., Shen, G. , Lindhard, S. & Brunoe, T. (2016) Factors affecting schedule delay, cost overrun, and quality level in public construction projects, Journal of Management in Engineering, 32 (1), 1-29. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000391
[22] Mahamid, I. (2020). Study of relationship between rework and labor productivity in building construction projects. Revista de la Construcción. Journal of Construction, 19 (1), 30-40. DOI: 10.7764/RDLC.19.1.30-41
[23] Mba, M. F. B., & Agumba, J. N. (2018). Critical success factors influencing performance outcome of joint venture construction projects in South Africa: Comparison of first and second order models. Construction Economics and Building, 18(3), 74-94. https://doi.org/10.5130/AJCEB.v18i3.5885
[24] Modi, H. J., Pathak, V. B., & Yadav, N. B. (2017). Analysis top crucial factors of contract clauses and quality in construction projects using RII method. International Journal of Emerging Technologies and Innovative Research, 4 (5), 239-243.
[25] Oke, A., Ogungbile, A., Oyewobi, L., & Tengan, C. (2016). Economic development as a function of construction project performance. Journal of Construction Project Management and Innovation, 6(2), 1447-1459.
[26] Ortega, I. (2000). Systematic prevention of construction failures. Institut Für Technologie Management (ITEM), 9, 1-13.
[27] Othman, N. A. & Mydin, M. A. O. (2014). Poor workmanship in construction of low cost housing. Analele Universitatii 'Eftimie Murgu', 21(1), 300-306.
[28] Pinto, J. K., & Mantel, S. J. (1990). The causes of project failure. IEEE Transactions on Engineering Management, 37(4), 269-276.
[29] Pol, P. A. & Konnur, B. A. (2017) Evaluation of success factors in construction industry by using RII. International Journal of Novel Research and Development, 2(4), 30-34.
[30] Ranawat, H. S., Bhadoriya, G., & Trivedi, M. (2018). Critical factors which are affecting the success of construction project in Gwalior division, India. International Journal of Applied Engineering Research, 13(11), 10108–10114.
[31] Santoso, D. S. & Gallage, P. G. M. P. (2019). Critical factors affecting the performance of large construction projects in developing countries: A case study of Sri Lanka. Journal of Engineering, Design and Technology, 18 (3), 531-556. https://doi.org/10.1108/JEDT-05-2019-0130
[32] Shanmugapriya, S. & Subramanian, K. (2015). Structural equation model to investigate the factors influencing quality performance in Indian construction projects. Sadhana. 40(6), 1975-1987. DOI: 10.1007/s12046-015-0421-3
[33] Sheikh, A. H. A. , Ikram, M. , Ahmad, R. M. , Qadeer, H. & Nawaz, M. (2019). Evaluation of key factors influencing process quality during construction projects in Pakistan. Grey Systems: Theory and Application, 9 ( 3), 321-335. https://doi.org/10.1108/GS-01-2019-0002
[34] Singh, M. & Sharma, S. K. (2020). Critical Success Factors in Construction Projects. International Journal of Recent Technology and Engineering (IJRTE), 8 (5). DOI:10.35940/ijrte.E6408.018520
[35] Toor, S. and Ogunlana, S. O. (2008). Critical COMs of success in large-scale construction projects: Evidence from Thailand construction industry. International Journal of Project Management ,26, 420–430. doi:10.1016/j.ijproman.2007.08.003
[36] Vadivel, T. S., Doddurani, M., Shobana, K. S., & Kalidhass, B. (2016). Analyzing the factors affecting quality in construction. International Journal of Engineering Research & Technology (IJERT) NCCETCE, 4 (33),1-6.
[37] Zehro, K., & Jkhsi, S. (2020). Management, quality and economy in home building construction. International Journal of Advanced Engineering, Sciences and Applications, 1(2), 12-17.
[38] Zikmund, W. G., Babin, B. J., Carr, J. C., & Griffin, M. (2008). Business Research Methods (8th ed.). Mason.
Copyright (c) 2021 Review of Applied Socio-Economic Research

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Copyright ©2019 Pro Global Science Association
All rights reserved. No part of this publication may be reproduced, stored, transmitted or disseminated, in any form, or by any means, without prior written permission from Pro Global Science Association, to whom all requests to produce copyright material should be directed, in writing.